Posted Wednesday, May 8, 2019

From the Public Works Department

2019 Road Work Schedule

Below is the 2019 roadwork schedule. This schedule is dependent on weather. Please check back regularly for changes and/or updates.   

Crack sealing: week of May 13 

Geyers Church Rd

Steinruck Rd

Oakview Cir

Miller Rd

Landvater Rd

Line painting: week of May 20

Geyers Church Rd

Locust Grove Rd

Schoolhouse Rd

Foxianna Rd

Newberry Rd

Steinruck Rd

Round Top Rd

Miller Rd

Red Bridge Rd

Pecks Rd

Across from 1611 Gingrich Rd: regrade swale: week of May 27 

190 Lauffer Rd: replace storm pipe: week of June 6 

Brinser Rd south of S Geyers Church Rd: regrade swale: week of June 10 

2535 Round Top Rd: replace storm pipe: week of June 18 

These projects will be scheduled as time, and weather allows.

3906 Snavely Rd: clean gutter, paving repairs

Newberry Rd @ Lauffer Rd: install underdrain, paving repairs

4649 Kennedy Ln: replace storm pipe

Swatara Creek Rd: mill road surface

Roadside mowing 

Tree trimming 

Pothole repairs